Cited by
Opinions in Minnesota that cite Krahn v. J. L. Owens Co., 161 N.W. 257.
-
Enviro-Fab, Inc. v. Blandin Paper Co.
349 N.W.2d 842
Minn. Ct. App. 1984
(Citations omitted) If the contracts are separate and distinct and unrelated, not in connection with a continuous work or job, a lien claim filed does not preserve a lien upon materials furnished prior to the 90 days Paine & Nixon Co. v. Dahlvick, 136 Minn. 57, 58
-
Rochester's Suburban Lumber Company v. Slocumb
163 N.W.2d 303
Minn. 1968
In Paine & Nixon Co. v. Dahlvick, 136 Minn. 57, 58 , , the court said: “* * * If the work being done is one continuous work constituting one job, though there are several agreements for the furnishing of different materials, each being a separate contract for some part of the general work, a lien claim filed within 90 days after the last item preserves a lien for all.
-
New Prague Lumber & Readi-Mix Co. v. Bastyr
117 N.W.2d 7
Minn. 1962
In Paine & Nixon v. Dahlvick, 136 Minn. 57, 59 , , we held that: “If the contracts are separate and distinct and unrelated, not in *257 connection with a continuous work or job, a lien claim filed does not preserve a lien upon materials furnished prior to the 90 days.” In Villaume Box & Lbr.
-
Kahle v. McClary
96 N.W.2d 243
Minn. 1959
2 E. g., Paine & Nixon Co. v. Dahlvick, 136 Minn. 57 , ; Fitzpatrick v. Ernst, 102 Minn. 195 , ; Dayton v. Minneapolis Radiator & Iron Co. 63 Minn. 48 , ; 12 Dunnell, Dig.
-
Barrett v. Hampe
53 N.W.2d 803
Minn. 1952
2 In Paine & Nixon Co. v. Dahlvick, 136 Minn. 57, 58 , , we stated as a general rule: “* * * The only question is whether the finding is sustained by the evidence.
- Valencia v. Markham Co-Operative Assn. 297 N.W. 736 Minn. 1941
-
Valencia v. Markham Co-Operative Assn.
297 N.W. 736
Minn. 1941
See Krahn v. J. L. Owens Co. 136 Minn. 53 , ; Id.
-
Lake Street Sash & Door Co. v. D. H. Evans Co.
243 N.W. 110
Minn. 1932
ted in the building in order to complete the job of the contractor); Minneapolis S. & D. Co. v. Hedden, 131 Minn. 31 , (the finding was that a drain board, though by mistake delivered to an adjacent building and lost, was in fact furnished for the construction of the building on which the lien was asserted and therefor licuable); Paine & Nixon Co. v. Dahlvick, 136 Minn. 57 , (the finding was that the last materials were furnished under a contract for an improvement not contemplated when
-
Henry Simons Lumber Co. v. Schnobrich
198 N.W. 406
Minn. 1924
ows: “When the owner determines to add something to the building after its construction has been completed and it has been delivered and accepted, materials furnished to the contractor to make the addition and not to accomplish the general purpose of the original contract are considered to be furnished under a new and independent contract.” And in Paine & Nixon Co. v. Dahlvick, 136 Minn. 57 , , where the question was one of fact, the court said: “If the work being done is one continuous work
- Friend v. Friend 196 N.W. 814 Minn. 1924
-
Friend v. Friend
196 N.W. 814
Minn. 1924
Krahn v. J. L. Owens Co. 136 Minn. 53 , .
-
Northland Pine Co. v. Newstrom
182 N.W. 612
Minn. 1921
Frankoviz v. Smith, 34 Minn. 403 , ; Paine & Nixon Co. v. Dahlvick, 136 Minn. 57 , ; see also 27 Cyc.
-
Villaume Box & Lumber Co. v. Condon
178 N.W. 492
Minn. 1920
Frankoviz v. Smith, 34 Minn. 403 , ; Fitzpatrick v. Ernst, 102 Minn. 195 , ; N. W. L. & W. Co. v. Parker, 118 Minn. 211 , ; Paine & Nixon Co. v. Dahlvick, 136 Minn. 57 , .
-
Carr-Cullen Co. v. Cooper
175 N.W. 696
Minn. 1920
516; Northwestern L. & W. Co. v. Parker, 118 Minn. 211 , ; American Bridge Co. v. Honstain, 120 Minn. 329 , ; Paine & Nixon Co. v. Dahlvick, 136 Minn. 57 , , and Northland Pine Co. v. Melin, 142 Minn. 233 , .
- Krahn v. J. L. Owens Co. 165 N.W. 129 Minn. 1917
-
Krahn v. J. L. Owens Co.
165 N.W. 129
Minn. 1917
Krahn v. J. L. Owens Co. 136 Minn. 53 , .