Opinions in Minnesota that cite HP Droher & Sons v. Toushin, 85 N.W.2d 273.
-
Sustainable 9, LLC d/b/a Sustainable 9 Design + Build, Respondent,
Minn. Ct. App. 2025
Droher & (stating that whether a contractor properly performed on its contract is a question of fact).
-
Joey Gunderson, Appellant,
Minn. Ct. App. 2025
Droher & -79 (Minn. 1957) (performance).
-
David Schindele, Appellant,
Minn. Ct. App. 2025
Droher & see also Johnson, d at 87 (stating that “the lack of foundation .
- Distinctive Design Build, LLC v. Thomas Nelson, Installed Building Solutions II, LLC, ... Minn. Ct. App. 2024
- Distinctive Design Build, LLC v. Thomas Nelson, Installed Building Solutions II, LLC, ... Minn. Ct. App. 2024
- Michael Gavigan, Respondent, Minn. Ct. App. 2019
- State v. Joseph 636 N.W.2d 322 Minn. 2001
-
State v. Joseph
636 N.W.2d 322
Minn. 2001
Droher & Sons v. Toushin, 250 Minn. 490 , we stated, “Ordinarily, when a litigant is willing to gamble on the outcome of a lawsuit and sit silent when he has an opportunity to present evidence, he should be bound by the result, whatever it may be.” Id.
- Rands v. Forest Lake Lumber Mart, Inc. 402 N.W.2d 565 Minn. Ct. App. 1987
-
Rands v. Forest Lake Lumber Mart, Inc.
402 N.W.2d 565
Minn. Ct. App. 1987
Droher and Sons v. Toushin, 250 Minn. 490, 499
- Fudally v. Ching Johnson Builders, Inc. 360 N.W.2d 436 Minn. Ct. App. 1985
-
Fudally v. Ching Johnson Builders, Inc.
360 N.W.2d 436
Minn. Ct. App. 1985
Droher and Sons v. Toushin, 250 Minn. 490, 499
- Elk River Enterprises, Inc. v. Adams 357 N.W.2d 139 Minn. Ct. App. 1984
-
Elk River Enterprises, Inc. v. Adams
357 N.W.2d 139
Minn. Ct. App. 1984
Droher and Sons v. Toushin, 250 Minn. 490, 502 , see also Frame v. Hohrman, 229 Minn. 468
- Julian Johnson Construction Corp. v. Parranto 352 N.W.2d 808 Minn. Ct. App. 1984
-
Julian Johnson Construction Corp. v. Parranto
352 N.W.2d 808
Minn. Ct. App. 1984
Droher & Sons v. Toushin, 250 Minn. 490, 494
- Vreeman v. Davis 348 N.W.2d 756 Minn. 1984
-
Vreeman v. Davis
348 N.W.2d 756
Minn. 1984
Droher & Sons v. Toushin, 250 Minn. 490, 501 , we found the owner’s opinion, “standing alone,” to be of little probative value in the absence of any showing that the owner was familiar with the market value of similar property.
- City of Eveleth v. Ruble 225 N.W.2d 521 Minn. 1974
-
City of Eveleth v. Ruble
225 N.W.2d 521
Minn. 1974
nable cost of $17,452.00, plus contractor overhead and profit (20%) in the amount of $3,490.40, and engineering and inspection (15%) in the amount of $2,617.80, for a total of $23,560.20.” The memorandum made part of the order for judgment reads, in part: “The measure of damages in a case against an engineer appears to be patterned after the rule set down in H. P. Droher and *261 Sons v. Toushin, 250 Minn. 490 , .
- Northern Petrochemical Co. v. Thorsen & Thorshov, Inc. 211 N.W.2d 159 Minn. 1973
-
Northern Petrochemical Co. v. Thorsen & Thorshov, Inc.
211 N.W.2d 159
Minn. 1973
Marshall v. Marvin H. Anderson Const. Co. 283 Minn. 320 , H. P. Droher & Sons v. Toushin, 250 Minn. 490 , Restatement, Contracts, § 346.
- Jackson v. Buesgens 186 N.W.2d 184 Minn. 1971
-
Jackson v. Buesgens
186 N.W.2d 184
Minn. 1971
Under such circumstances, as far as the real estate is concerned, the rule we applied in H. P. Droher & Sons v. Toushin, 250 Minn. 490 , 85 N. W. (2d) 273 , restricts recovery to the cost of repairing the defects, plus a reasonable amount for the loss of use of the basement and damage to personal property.
- Marshall v. Marvin H. Anderson Construction Co. 167 N.W.2d 724 Minn. 1969
-
Marshall v. Marvin H. Anderson Construction Co.
167 N.W.2d 724
Minn. 1969
Defendant cites only one case which it claims to be controlling —H. P. Droher & Sons v. Toushin, 250 Minn. 490 , 85 N. W. (2d) 273 .
- Breza v. Thaldorf 149 N.W.2d 276 Minn. 1967
-
Breza v. Thaldorf
149 N.W.2d 276
Minn. 1967
4 H. P. Droher & Sons v. Toushin, 250 Minn. 490 , 85 N. W. (2d) 273 ; Independent School Dist.
- Crea v. Hall 122 N.W.2d 610 Minn. 1963
-
Crea v. Hall
122 N.W.2d 610
Minn. 1963
Authorities cited by plaintiff include Podgorski v. Kerwin, 147 Minn. 103 , ; Amland v. Grose, 208 Minn. 596 , ; Parrish v. Peoples, 214 Minn. 589 , 9 N. W. (2d) 225 ; In re Estate of Liberopulos, 245 Minn. 553 , 73 N. W. (2d) 607 ; and H. P. Droher & Sons v. Toushin, 250 Minn. 490 , 85 N. W. (2d) 273 .
- Prodger v. Zell 113 N.W.2d 168 Minn. 1962
-
Prodger v. Zell
113 N.W.2d 168
Minn. 1962
For a discussion of the measure of damages in a breach of contract, see H. P. Droher & Sons v. Toushin, 250 Minn. 490 , 85 N. W. (2d) 273 .
- Fussner v. Andert 113 N.W.2d 355 Minn. 1961
- Housing and Redevelopment Authority v. Zweigbaum 100 N.W.2d 719 Minn. 1960
-
Housing and Redevelopment Authority v. Zweigbaum
100 N.W.2d 719
Minn. 1960
H. P. Droher & Sons v. Toushin, 250 Minn. 490 , 85 N. W. (2d) 273 .