The holding in the court’s own words
Considering the totality of the circumstances, we conclude that the district court did not abuse its discretion in determining that the Crandalls failed to sufficiently notify Hanson and spoliated evidence by destroying the retaining walls. And because the Crandalls have not met their difficult burden to demonstrate that no reasonable person would agree with the court’s imposition of the sanction it imposed, we conclude that the district court also acted within its discretion in fashioning an appropriate sanction. We therefore conclude that the district court did not err in dismissing the Crandalls’ claims.
Quoted verbatim from the opinion — no paraphrase, nothing generated. Not yet human-reviewed. How we find the holding.
Authorities cited
Identified automatically; this list may not be exhaustive.
- Miller v. Lankow 801 N.W.2d 120
- Patton v. Newmar Corp. 538 N.W.2d 116
- Antone v. Mirviss 720 N.W.2d 331
- State Ex Rel. Cooper v. French 460 N.W.2d 2
- Star Centers, Inc. v. Faegre & Benson, L.L.P. 644 N.W.2d 72
- Logan v. Norwest Bank Minnesota, N.A. 603 N.W.2d 659
- Laska v. Anoka County 696 N.W.2d 133
- Laura L. Walsh v. U.S. Bank, N.A. 851 N.W.2d 598
- Johnson v. Garages, Etc., Inc. 367 N.W.2d 85
Opinion text
This opinion is nonprecedential except as provided by
Minn. R. Civ. App. P. 136.01, subd. 1(c).
STATE OF MINNESOTA
IN COURT OF APPEALS
A24-1054
Daniel W Crandall, et al.,
Appellants,
vs.
James E Hanson,
Respondent.
Filed March 17, 2025
Affirmed
Schmidt, Judge
Olmsted County District Court
File No. 55-CV-21-2026
David W. VanDerHeyden, VanDerHeyden Law Office, P.A., Rochester, Minnesota (for
appellants)
Christopher W. Bowman, Madigan, Dahl & Harlan, P.A., Minneapolis, Minnesota (for
respondent)
Considered and decided by Johnson, Presiding Judge; Larkin, Judge; and Schmidt,
Judge.
NONPRECEDENTIAL OPINION
SCHMIDT, Judge
The district court excluded appellants’ evidence obtained after a certain date as a
spoliation sanction and then , on respondent ’s motion for summary judgment, dismissed
appellants’ claims related to an alleged breach of a construction contract. On appeal ,
appellants argue the district court (1) abused its discretion in the spoliation and sanction
2
rulings, and (2) erred in determining that there w ere no genuine issue s of material fact
related to damages. We affirm.
FACTS
Appellants Daniel and Lorean Crandall 1 and respondent James Hanson are
neighbors. Hanson has over 35 years of experience constructing retaining walls. In the
summer of 2019, Daniel contacted Hanson about building retaining walls at the Crandalls’
residence. The parties entered into an oral contract for the construction of the retaining
walls. They dispute some of the terms, but it is undisputed that they agreed that the
Crandalls would pay Hanson for his labor, skill, and material s used to construct the
retaining walls. Daniel also agreed to work on the project and use some of his equipment.
Construction began in August 2019 and continued into October 2019. Sometime in
October, Hanson told the Crandalls that , because of the fall weather, it would be best for
Hanson to return in the spring of 2020 to complete the walls. The Crandalls disagreed,
believing that the walls could be finished in 2019. On October 31, 2019, Daniel sent a
letter notifying Hanson that the project was defective and incomplete, and gave Hanson a
deadline of November 30, 2019, to remedy the situation. The letter read:
There have been weeks of nice weather that you could have
been fulfilling this obligation. You are working on other jobs,
leaving ours totally abandoned, so it is clear you have made
your choice.
This puts me in an undesirable position. This job was going to
take two weeks. You started in July; it is now November. Had
this job been done on time, I would have been able to have my
patio poured and my driveway poured and moving on to the
1 The opinion refers to appellants by their first name or collectively as “the Crandalls.”
3
rest of my landscaping. As it is, I have a dirt driveway and
pallets for a patio. I am now at the back of the list with other
contractors.
We have been advised by Legal Counsel to take this first step
and give you the opportunity to complete our job, and do it
correctly, based on Dan’s interpretation of the original
agreement! That was based on all materials and labor.
The wall is defective, unfinished and is sinking in again. The
wall foundation needs to be sitting on virgin soil, or this
problem will never go away.
Deadline for completion is November 30, 2019. If not
completed, you can expect the next step, which will be Legal
action.
In addition, I want $1700 cash refund for block that was not
$500 more expensive, and the $1200 to rebuild the wall that I
said I would pay you if Dynamic
2 didn’t pay you. Dynamic
paid you $2000 to do the job.
If the job is completed to satisfaction and on time, I will let the
other overcharges from the original bid slide. If I am forced to
litigate this issue, I will need to include every expense past,
present and future, for another company to come in and do the
job over. I have been told that they would only take this job on
if they tear everything down and redo the foundation and
rebuild to their standards.
This is what I meant about a can of worms.
Twelve days later, Hanson responded to the letter with a text message explaining that he
could not complete the retaining walls until the spring due to the frozen ground.
In the spring of 2020, Hanson did not return to complete the work. On June 3, 2020,
2 Dynamic Masonry Products is the business that sold the retaining wall blocks.
4
the Crandalls’ attorney sent a letter to Hanson, which read, in relevant part:
Mr. and Mrs. Crandall have requested my assistance in
resolving this matter in light of your abandonment of this
retaining wall project. You have been paid $11,700.00 and
have had numerous opportunities to remedy your deficient and
improper work. My clients have obtained two bids to bring the
project into a condition where a properly built wall may be
constructed. Both of those estimates are in excess of
$40,000.00. My clients believe that your deficient work will
cause them and has caused them monetary damages and that a
jury would find for them in at least that amount.
Hanson did not respond to the letter or inspect his work on the retaining walls.
In July 2020, the Crandalls hired an expert to inspect the retaining walls. The expert
informed the Crandalls that he did not believe the walls were installed correctly because
there was no footing under the retaining walls; one of the walls was sagging, which opened
voids between the blocks and allowed water to wash through the blocks; and the walls were
bowed in several areas. The expert also discovered there was no permit obtained for the
retaining walls, as required by Minnesota’s building code. The expert recommended that
the walls be torn down and replaced. The Crandalls sought bids and eventually replaced
the retaining walls sometime around September 2020.
The Crandalls sued Hanson in September 2020, alleging four counts in their
complaint: (1) breach of contract; (2) breach of state building code requirements;
(3) negligent design and construction; and (4) fraud/misrepresentation. T he Crandalls
alleged that Hanson had unilaterally abandoned the project; Hanson had many
opportunities to remedy the deficient work; the cost to remediate and repair the project was
$41,616.47; and the Crandalls had already paid Hanson $11,200.
5
Hanson moved for summary judgment in February 2022, alleging that the Crandalls
spoliated evidence by failing to provide Hanson with notice and an opportunity to inspect
the retaining walls before they were replaced , which prejudiced Hanson’s ability to wage
a defense.3 The Crandalls opposed the motion, arguing that Hanson was fully aware of the
defects and had ample opportunity to correct his work. They also argued that Hanson had
time to inspect the walls before they were replaced and that replacement of the walls was
necessary to prevent further damage to their property.
The district court found that the Crandalls spoliated evidence because they “did not
sufficiently provide Hanson a full and fair opportunity to inspect the retaining walls.” The
court elaborated:
The Crandalls rely on the letter they sent Hanson on
October 31, 2019. The letter stated that Hanson had until
November 30, 2019, to complete the project and if not, the
Crandalls would treat Hanson as if he abandoned the project.
It also mentioned that if the Crandalls had to go with another
contractor, he or she would need to replace the retaining walls
and start fresh. The letter did not say the Crandalls had plans
to replace the retaining walls. The letter essentially only
provided a deadline to com plete the retaining wall and
contained warnings about the potential costs if they had to go
with another contractor. The Crandalls sent no other notices to
Hanson after they decided to move forward with replacing the
retaining walls nearly a year later in September 2020. As such,
the Crandalls did not satisfy the notice requirement in Miller
[v. Lankow, 801 N.W.2d 120 (Minn. 2011)] and have spoliated
evidence.
3 Hanson also argued that he was entitled to summary judgment on the Crandalls’ claim
for fraud /misrepresentation. The district court agreed and dismissed the claim. The
Crandalls do not challenge the dismissal of their fraud/misrepresentation claim on appeal.
6
The district court did not address the June 3, 2020 , letter in its opinion because the letter
was not part of the record at the time of the summary judgment proceeding. As a sanction
for spoliating evidence, the district court ruled that any evidence that the Crandalls obtained
after October 31, 2019, would be excluded.
On May 1, 2024, long after discovery closed and days before trial was set to
commence, the Crandalls submitted their second supplemental answers to Hanson’s
interrogatories. In their supplemental answer to an interrogatory requesting a detailed
description of claimed damages, the Crandalls stated they were “claiming damages for
breach of contract in the amount of $41,616.47.” The Crandalls explained that this
computation of damages was based on their election “to recover the amount based upon
the difference between the value of the property before and after the harm (the fair market
value of the property on October 31, 2019 minus the fair market value, if any, of what
remains of the property after damage).” This was the first time during the multiyear
litigation that the Crandalls explicitly articulated a diminution-in-value theory of damages.
On May 2, 2024, Hanson moved for summary judgment on the Crandalls’ remaining
claims, arguing that the Crandalls have not produced admissible evidence to support any
recoverable damages due to the spoliation sanction. Hanson also argued that the Crandalls
failed to timely disclose their diminution -in-value damages calculation. In opposition to
the motion, the Crandalls argued that Hanson was on notice that the Crandalls were seeking
diminution-in-value damages from the start of the case. They also asserted that there was
evidence of damages that predated October 31, 2019 , in the amount of $11,200 for the
amounts paid by the Crandalls to Hanson during construction.
7
On May 6, 2024—the morning of trial —the district court addressed the motion ,
noting that the Crandalls’ diminution-in-value damages theory was not properly noticed ,
but that the $11,200 that the Crandalls paid to Hanson could be recoverable damages. But
after Hanson’s counsel argued that damages in a construction case are limited to either the
cost of reconstruction or diminution of value —and that a contract payment , like the
$11,200, was not a valid measure of damages—the district court granted Hanson’s motion.
The court filed its written order the next day, dismissing the complaint “on the basis that
damages are speculative, remote, or conjectural.” This appeal follows.
DECISION
The Crandalls raise two issues on appeal. First, they argue that the district court
abused its discretion by ordering a spoliation sanction. Second, they contend that the
district court erred in finding no genuine issues of material fact exist with respect to
damages and erred in its application of the law. We address these issues in turn.
I. The district court did not abuse its discretion by imposing a spoliation sanction.
The Crandalls argue the district court abused its discretion by finding they spoliated
evidence and, thereafter, by imposing a sanction. “We review a district court’s decision to
impose spoliation sanctions for abuse of discretion.” Miller, 801 N.W.2d at 127.
We first address whether the district court abused its discretion in finding that the
Crandalls spoliated evidence. A party has a duty to preserve evidence when they know or
should know that litigation is reasonably foreseeable. Id. at 127-28. A breach of the duty
to preserve evidence may be sanctioned, “under a court’s inherent authority, as spoliation.”
Id. at 128. But the duty to preserve evidence is not boundless and “must be tempered by
8
allowing custodial parties to dispose of or remediate evidence when the situation
reasonably requires it.” Id. A “custodial party with a legitimate need to destroy evidence
may be absolved of a failure to preserve evidence by providing sufficient notice and a full
and fair opportunity to inspect the evidence to a noncustodial party.” Id. at 129.
The district court found that “the Crandalls did not sufficiently provide Hanson a
full and fair opportunity to inspect the retaining walls.” The court noted that the
October 2019 letter “did not say the Crandalls had plans to replace the retaining walls [but]
essentially only provided a deadline to complete the retaining wall[s] and contained
warnings about the potential costs if they had to go with another contractor.” The d istrict
court added that “[t]he Crandalls sent no other notices to Hanson after they decided to move
forward with replacing the retaining walls nearly a year later in September 2020.”
When evaluating the sufficiency of a notice, a district court should consider the
totality of the circumstances. Id. at 131. A notice will usually be sufficient if it indicates
“the time and nature of any action likely to lead to destruction of the evidence, and offering
a full and fair opportunity to inspect[.]” Id. at 132.
The Crandalls argue that the June 2020 letter, together with the October 2019 letter,
demonstrate that Hanson had a full and fair opportunity to inspect prior to destruction of
the wall. Hanson argues that the June 2020 letter should be set aside because it was not
made available for review by the district court at the time of the court’s ruling . Hanson
also contends that neither letter provided valid notice or the opportunity to inspect.
The district court did not err. The October 2019 letter only provided a deadline for
Hanson to complete the retaining walls and included warnings about the potential costs if
9
a new contractor was needed. It did not address the extent to which evidence would be
destroyed, the approximate date of when it would be destroyed, or offer Hanson an
opportunity to inspect the evidence. Even if we were to consider the June 2020 letter—
which was not before the district court at the summary judgment stage—the letter is simply
a demand letter from the Crandalls’ attorney. While the letter explained that the Crandalls
had obtained two bids to reconstruct the retaining walls and noted their desire to resolve
the matter, the letter does not provide Hanson an opportunity to inspect the walls or detail
when— or even if—the Crandalls planned to replace the walls. Considering the totality of
the circumstances, we conclude that the district court did not abuse its discretion in
determining that the Crandalls failed to sufficiently notify Hanson and spoliated evidence
by destroying the retaining walls.
We next turn to whether the district court abused its discretion by imposing a
sanction. The supreme court has adopted three factors for district courts to consider when
determining whether to impose sanctions for a custodial party’s destruction of evidence:
(1) the degree of fault of the party who altered or destroyed the
evidence; (2) the degree of prejudice suffered by the opposing
party; and (3) whether there is a lesser sanction that will avoid
substantial unfairness to the opposing party and, where the
offending party is seriously at fault, will serve to deter such
conduct by others in the future.
Id. (quotation omitted). In fashioning a sanction, a court must “examine the nature of the
item lost in the context of the claims asserted and the potential for remediation of the
prejudice” to the opposing party. Patton v. Newmar Corp., 538 N.W.2d 116, 119 (Minn.
1995). A party challenging a “choice of a sanction has the difficult burden of convincing
10
an appellate court that the [district] court abused its discretion—a burden which is met only
when it is clear that no reasonable person would agree with the [district] court’s assessment
of what sanctions are appropriate.” Id. (quotation omitted).
The Crandalls argue that the district court abused its discretion by not analyzing the
three factors be fore imposing a sanction. Although the district court may not have
expressly named the factors, our review of the record shows that the court appropriately
analyzed the factors when imposing the sanction. First, t he district court found that the
Crandalls were at fault for demolishing and replacing the retaining walls without notice to
Hanson. Second, the district court found that Hanson suffered prejudice “because he was
not able to examine the retaining walls to determine the extent of the damage s at the time
the retaining walls were replaced.” And third, the district court imposed the
least-restrictive sanction that it determined would avoid substantial unfairness to Hanson.
As the court explained, the Crandalls had the opportunity to hire an expert to inspect
the retaining walls and provide an opinion about the quality of the walls. Hanson was not
afforded this opportunity. Had Hanson received sufficient notice while the walls remained
intact, Hanson could have inspected them or hired an expert to review the quality of work
and the costs of repair. The Crandalls’ spoliation of evidence deprived Hanson of his
opportunity to defend against the allegation that he was at fault for the defective walls and
diminished his ability to develop an informed position on any damages the Crandalls may
have suffered. Within its discretion, the district court determined that a llowing evidence
obtained after the parties’ relationship ceased—evidence that Hanson would not have had
the opportunity to counter—would have prejudiced Hanson.
11
On this record, the district court acted well within its discretion in deciding that the
Crandalls spoliated evidence. And because the Crandalls have not met their difficult
burden to demonstrate that no reasonable person would agree with the court’s imposition
of the sanction it imposed, we conclude that the district court also acted within its discretion
in fashioning an appropriate sanction.
II. The district court did not err by dismissing the Crandalls’ claims.
The Crandalls argue that the district court erred by dismissing their claims because
genuine issues of material fact for trial remain. Given that the district court referred to
information provided in discovery that was not included or referenced in the pleadings, we
treat the district court’s order as one granting summary judgment. See Antone v. Mirviss,
720 N.W.2d 331, 334 n.4 (Minn. 2006) (stating that when a district court considers matters
outside the pleadings, a motion to dismiss should be treated as one for summary judgment).
In an appeal from summary judgment, we determine whether there is a genuine issue
of material fact for trial and whether the district court erred in its application of the law.
State by Cooper v. French , 460 N.W.2d 2, 4 (Minn. 1990). The standard of review is
de novo. STAR Ctrs., Inc. v. Faegre & Benson, L.L.P., 644 N.W.2d 72, 77 (Minn. 2002).
The district court dismissed the remaining claims based on the Crandalls’ inability
to prove damages. See Logan v. Norwest Bank Minn., N.A., 603 N.W.2d 659, 663 (Minn.
App. 1999) (providing that damages are an essential element of a breach -of-contract
claim); Laska v. Anoka County, 696 N.W.2d 133, 137 (Minn. App. 2005) (providing that
damages are an essential element of a negligence claim). The court reasoned that (1) the
Crandalls did not give Hanson proper notice that their damages claim would be based on a
12
theory of the diminution of value, and (2) the two checks totaling $11,200 for payment to
Hanson by the Crandalls for work Hanson performed on the retaining walls was not a valid
measure of damages in a case involving a construction contract.
As to the Crandalls’ diminution-in-value theory, we agree with the district court’s
determination. This damages theory was first raised in the Crandalls’ second supplemental
answers to Hanson’s interrogatories , which were submitted only days before trial was
scheduled to commence . Before this, the Crandalls simply listed several documents—
without explanation— in response to discovery requests to detail their claimed damages.
While we recognize that Minnesota is a notice-pleading state, see Walsh v. U.S. Bank, N.A.,
851 N.W.2d 598, 604-05 (Minn. 2014), waiting until several days before trial to respond
to discovery and detail the damages claimed in a multiyear litigation does little to ensure
fairness and to allow the opposing party to adequately prepare.
We also agree with the district court that the checks are not evidence of a recognized
measure of damages for this construction case. Minnesota law is clear that the appropriate
measure of damages for breach of a construction contract is either the cost of reconstruction
or diminution of value. Johnson v. Garages, Etc., Inc., 367 N.W.2d 85, 86 (Minn.
App. 1985). And we have reversed an award of damages based on the original cost of
construction because “[t]here is no Minnesota law holding that the measure of damages for
breach of a construction contract is the breaching party’s cost for that portion of the contract
which is in breach.” Id. at 87. Because Minnesota law does not recognize construction
costs—like the payments —as damages in a breach-of-construction-contract case like this,
the amount paid by the Crandalls cannot be the measure of damages.
13
Without admissible evidence to support their claimed damages, there is no genuine
issue as to any material fact. We therefore conclude that the district court did not err in
dismissing the Crandalls’ claims.
Affirmed.