The holding in the court’s own words
5 Because we conclude that the Braun report was not incorporated into the contract, we do not reach a decision on Ames’ differing site-conditions argument.
Quoted verbatim from the opinion — no paraphrase, nothing generated. Not yet human-reviewed. How we find the holding.
Authorities cited
Identified automatically; this list may not be exhaustive.
- Montemayor v. Sebright Products, Inc. 898 N.W.2d 623
- Alpha Real Estate Co. of Rochester v. Delta Dental Plan of Minnesota 664 N.W.2d 303
- Knudsen v. TRANPSORT LEASING/CONTRACT, INC. 672 N.W.2d 221
- McCree & Company v. State 91 N.W.2d 713
- L. J. McNulty, Inc. v. Village of Newport 187 N.W.2d 616
Opinion text
This opinion is nonprecedential except as provided by
Minn. R. Civ. App. P. 136.01, subd. 1(c).
STATE OF MINNESOTA
IN COURT OF APPEALS
A25-0754
Ames Construction Inc.,
Appellant,
vs.
City of Moorhead,
Respondent.
Filed March 30, 2026
Affirmed
Worke, Judge
Clay County District Court
File No. 14-CV-23-3834
Dean B. Thomson, Robert L. Smith, Elise R. Radaj, Fabyanske, Westra, Hart & Thomson,
P.A., Minneapolis, Minnesota; and
Alethea M. Huyser, Fredrikson & Byron, P.A., Minneapolis, Minnesota (for appellant)
James J. Thomson, Michelle E. Weinberg, Kennedy & Graven, Chartered, Minneapolis,
Minnesota (for respondent)
James J. Hartnett, Joshua T. Peterson, Faegre Drinker Biddle & Reath LLP, Minneapolis,
Minnesota; (for amicus Associated General Contractors of Minnesota)
Justin P. Short, Elizabeth R. Cox, Best & Flanagan, LLP, Minneapolis, Minnesota (for
amicus Minnesota Asphalt Pavement Association)
Keith Ellison, Attorney General, Erik M. Johnson, Mathew Ferche, Assistant Attorneys
General, St. Paul, Minnesota (for amicus Commissioner of Transportation)
Considered and decided by Worke, Presiding Judge; Ross, Judge; and Bratvold,
Judge.
2
NONPRECEDENTIAL OPINION
WORKE, Judge
Appellant challenges the district court’s summary-judgment decision, arguing that
respondent city is liable because it provided an inaccurate geotechnical report when
advertising the project for bids. Respondent asserts the plain language of the contract is
determinative and the bid solicitation was not part of the contract documents and, as such,
is not liable. We affirm.
FACTS
The undisputed evidence, derived from the district court’s summary-judgment
record, shows the following. In 2002, respondent City of Moorhead began preliminary
work and environmental assessments for a construction project that would allow streets to
pass under new railroad bridges utilized by railroad companies. SRF Consulting Group
Inc. was retained by the city to prepare plans and specifications for the project. SRF
subcontracted with Braun Intertec Corporation for a geotechnical evaluation. Braun
completed the geotechnical evaluation and provided a report (the Braun report) in 2008.1
By 2009, the city completed most of the project plans.
After the plans were completed, the project was put on hold until 2018 due to a lack
of funding. In March of 2018, the city received sufficient funding and opened the project
for public bidding. Information was made available to bidders in a “bid packet,” including
the contract documents, attachments, bidder requirements , and the bidding timeline. The
1 The Braun report was a 283-page geotechnical engineering report assessing the soil
conditions at the project site.
3
Braun report was included as an attachment labeled “Geotechnical Report.” Appellant
Ames Construction Inc. submitted a proposal and was awarded the project.
SRF designed permanent portions of the project, but Ames was responsible for
designing any temporary earth-retention systems. Ames subcontracted with an engineering
firm for the design of temporary retention systems. The engineering firm used the Braun
report when designing the temporary systems for Ames’ construction plans.
The temporary retention systems experienced soil movement and slope failures,
which delayed and increased project costs. From 2018 to 2020, these issues were prevalent.
Following the failures, the railroad company required that Ames’ plans be revised and
resubmitted for approval before further excavation.
The project was halted to accommodate further soil-condition investigations. Ames
engaged another engineering firm to conduct those investigations, alleging that Braun’s
geotechnical report was inaccurate. The firm issued findings showing the project’s
structures required redesign and a new submittal review process was created. Because of
the failures, required redesigns, and changes to processes, Ames had to delay the project’s
anticipated completion date. Ames incurred additional costs totaling approximately
$15,274,924.
In 2023, Ames filed suit in district court against the city, alleging breach of contract,
breach of implied warranties, unjust enrichment, and declaratory judgment because the
subsurface soil conditions were materially different than those in the Braun report. The
city filed an answer and counterclaim alleging declaratory judgment and contractual
indemnification. In 2024, the parties filed competing motions for summary judgment. The
4
district court granted the city’s motion and denied Ames’ motion. In relevant part, the
district court concluded that the Braun report was not part of the contract the city and Ames
entered into and thus created no implied warranty. This appeal followed.
DECISION
Ames argues that the district court erred in its summary-judgment decision by
concluding that the Braun report was not part of the contract. W e review summary-
judgment determinations de novo “to determine whether there are genuine issues of
material fact and whether the district court erred in its application of the law.” Montemayor
v. Sebright Prods., Inc., 898 N.W.2d 623, 628 (Minn. 2017) (quotation omitted).
The Braun Report
Ames argues that the district court erred by concluding that the Braun report was
not part of the contract because the report was a contract document under the agreement’s
plain language.
Interpreting a written contract is a question of law reviewed de novo. Alpha Real
Estate Co. of Rochester v. Delta Dental Plan of Minn., 664 N.W.2d 303, 311 (Minn. 2003).
Absent ambiguity, the terms of a contract are given their plain and ordinary meaning.
Knudsen v. Transp. Leasing/Contr., Inc., 672 N.W.2d 221, 223 (Minn. App. 2003), rev.
denied (Minn. Feb. 25, 2004). If a contract is unambiguous, “a court gives effect to the
parties’ intentions as expressed in the four corners of the instrument.” Id.
The parties dispute the district court’s interpretation of the term “bid packet.” Ames
argues that, when all the documents were condensed into one PDF file and made available
to bidders, the Braun report was incorporated as a contract document. We disagree.
5
Per Article V of the contract, “Contract Documents” consist of the following
sections:
(1) Advertisement for Bids
(2) Instruction to Bidders
(3) Form of Proposal / Bid Packet
(4) General Specifications
(5) Special Provisions
(6) Specifications
(7) Plans and Drawings which are attached to the
specifications.
(8) This instrument and the Payment & Performance
Bonds.
As the district court noted, there is no express section or form labeling or defining
the term “bid packet.” However, the plain language of the contract does not include the
Braun report as a contract document in Article V. Under “Instruction to Bidders,” it states:
All papers bound with or attached to the “Bid Packet” are a
necessary part thereof and must not be detached. The Bid
Packet shall include the Form of Proposal, the Certification of
Compliance of Responsible Contractors, List of Materials
Suppliers, Non-Collusion Affidavit, and Certificate of
Compliance with MN Worker’s Compensation Law.
(Emphasis added.)
Here, the instruction to bidders states that the bid packet includes: “the Form of
proposal, [] Certification of Compliance of Responsible Contractors, Lists of Materials
Supplies, Non- Collusion Affidavit, and Certificate of Compliance with [Minnesota]
Worker’s Compensation law.” These are documents bidders were required to submit to
acknowledge their familiarity with the local conditions affecting the cost of the work, the
general conditions, plans and specifications, and special provisions. In addition, Article V
only identifies eight components that are considered contract documents and does not
6
include any reference to attachments, which is where the Braun report was included. The
district court correctly concluded that interpreting the bid packet to include the Braun report
would expressly contradict the unambiguous language provided in the contract. Under the
contract’s plain language, bid packet does not reference or imply that the Braun report or
any geotechnical evaluations provided by the city would be considered part of a “bid
packet” or that such evaluations were intended to be a contract document.
This conclusion is further supported by looking at the index sheet, included in the
bid materials, which clearly identifies and lists what is included in the term “Contract
Documents.”2 The index sheet has four categories with documents listed under each
category. Categories include: “Contract Documents”; “General Specifications & City of
Moorhead Specifications”; “Special Provisions”; and “Attachments[.]” The list of
documents under “Contract Documents” are consistent with those in the language of
Article V.3 In the index, the Braun report is unambiguously listed as an “Attachment[,]”
and not included as a contract document.
Ames argues that the “bid packet” encompasses the entire document set that the city
made digitally available to bidders and, therefore, is part of the contract. As the district
court concluded, this argument contradicts the plain and unambiguous terms of the
contract. If the city intended for every document that was provided to bidders to be a
2 The record on appeal provides two versions of the Index Sheet. On review, it is unclear
where each appear within the documents provided during the bidding process. Both
versions, however, unambiguously include the Braun report as a “geotechnical report” in
the listed attachments.
3 Article V(6) is titled “Specifications” and section (7) includes the “Plans and Drawings”
which are attached to the specifications.
7
contract document, then parts of the contract would be rendered redundant. For example,
Article V, identifying the eight components that are “contract documents,” would be
unnecessary if every document provided to bidders was considered a contract document
under Ames’ argument.4 This also applies to the index sheet, which lists what documents
are “contract documents.” The Braun report is explicitly listed as an attachment, not a
contract document.
Neither the listed contract documents nor the specific papers required to be in the
bid packet referenced the Braun report or the attachment area where the Braun report was
located. This shows that the Braun report was not considered part of the contract. Thus,
the district court did not err in its conclusion that the Braun report was not a contract
document.5
The Spearin Doctrine
Ames next argues that the district court’s narrow interpretation of the Spearin
doctrine was erroneous.
The Spearin doctrine states that contractors are not excused or entitled to additional
compensation due to unforeseen difficulties, “[b]ut if the contractor is bound to build
according to the plans and specifications prepared by the owner, the contractor will not be
responsible for the consequences of defects in the plans and specifications.” McCree &
4 Ames also argues that the language in the contract’s general conditions and special
provisions demonstrates that the Braun report was part of the contract. However, the Braun
report was explicitly listed as an attachment and not a contract document. Thu s, any
argument that the report is implicitly within the document fails.
5 Because we conclude that the Braun report was not incorporated into the contract, we do
not reach a decision on Ames’ differing site-conditions argument.
8
Co. v. State, 91 N.W.2d 713, 722 (Minn. 1958) (quoting United States v. Spearin, 248 U.S.
132, 136 (1918)). Further, the “responsibility of the owner is not overcome by the usual
clauses requiring builders to visit the site, to check the plans, and to inform themselves of
the requirements of the work.” Id. (quotation omitted). Thus, an implied warranty exists
where an owner furnishes not only detailed plans and specifications, but also the particular
construction methods the contractor is required to follow. See id. at 724-25.
Here, Ames relies on the Braun report to support the existence of an implied
warranty under Spearin. But the district court correctly determined that the Braun report
was not a binding plan or specification and its inclusion in the materials provided to bidders
did not create an implied warranty. As the district court correctly reasoned, however, the
Braun report is neither a plan nor a specification under the terms of the contract.
The contract for the project incorporated the Minnesota Department of
Transportation’s 2018 Standard Specifications for Construction (MnDOT Standard
Specifications). MnDOT Standard Specifications defined “plans” as “[t]he plans, profiles,
typical cross-sections, and Standard Plans and Standard Plates that show the locations,
character, dimensions, and details of the work,” and “specifications” as “[t]he Standard
Specifications, the Supplemental Specifications, the Special Provisions, and any
Department-approved changes to these Contract documents.”
The Braun report fails to meet the definition of “plans” because it does not provide
design plans detailing the work for the project. While the Braun report does cover
temporary shoring, it does not provide a design plan detailing the requirements for any
temporary shoring methods. Similarly, the Braun report fails to meet the definition of
9
“specifications” because it does not provide requirements for any temporary-retention-
system methods. In fact, the design of temporary retention systems was “expressly
delegated” to Ames. In other words, Ames was not required to use the Braun report, nor
was it required to complete the temporary retention systems according to the information
within the report. The district court correctly reasoned that the city did not create an
implied warranty.
Even if we were to consider the Braun report as part of the contract, Spearin would
still not apply because the Braun report itself provided several disclaimers for the report’s
use in the design process for temporary retention systems. Specifically, the Braun report
repeatedly tells the reader that if designs, plans, or specifications change, Braun “should
be informed,” and further analyses and revised recommendations may be necessary. A
disclaimer in paragraph E.4. provides that “[t]he design of the temporary retaining
structures is not within the Scope of Services of the geotechnical report.” Paragraph E.4.b.
goes a step further, stating that “it is not the intent of this evaluation to design the temporary
shoring.” Lastly, paragraph K.4. provides that the report was made for the “exclusive use”
of the city, SRF, and railroad companies; and “[i]n the absence of our written approval,
[Braun] make[s] no representation and assumes no responsibility to other parties regarding
this report.” Paragraph K.4. continues, stating “[t]he data, analyses and recommendations
may not be appropriate for other structures or purposes.” These disclaimers provide that
(1) the temporary retention systems were not within the scope of services encompassed by
the report, (2) Braun did not intend for the report to cover temporary retention sys tem
10
designs, and (3) the report did not provide specific plans or specifications for the temporary
shoring systems.
With the disclaimers provided, this case is analogous to L.J. McNulty, Inc. v. Village
of Newport, 187 N.W.2d 616, 616-22 (Minn. 1971). In McNulty , a contractor sought
additional compensation for a water and sewer project. Id. 617-18. Like here, McNulty
relied on ground borings provided by the village during the bidding process. See id. at 618.
McNulty encountered issues after work commenced. Id. Partway through the project,
more borings were needed, and the project plans were altered. Id. McNulty, like Ames,
incurred extra costs due to these issues. See id. at 617. The supreme court affirmed
judgment in favor of the village, noting that “the village . . . told the bidders what
information was included in the plans, where it came from, who prepared it, how it was
prepared, and why.” Id. at 622. Like the Braun report, the supreme court noted that “the
village even pointed out what the information was not.” Id.
In sum, the Braun report was not a plan or specification that created an implied
warranty. Even if the report was included in the contract, the language of the Braun report
itself explicitly states that the recommendations for temporary retention systems were just
that—recommendations—not required plans or specifications detailing exactly how the
temporary shoring systems should be constructed. Accordingly, the district court did not
err by concluding that the Spearin doctrine did not apply.
Affirmed.