A26-0043 Nonprecedential Reversed and remanded Processed

Resolution Denying Petition for Environmental Assessment Worksheet for Fischer Pit Expansion Project.

Minnesota Court of Appeals · Filed August 3, 2026

The holding in the court’s own words

Because we conclude that the township erred by applying the wrong standard in assessing these concerns, we remand to the township. Applying these dictionary definitions, we conclude that the township’s use of “will have” improperly imposed a certainty standard on the Girgens’ petition. Thus, we conclude that the township erred in applying the wrong standard when it assessed the potential for significant environmental effects at this earlier stage.

Quoted verbatim from the opinion — no paraphrase, nothing generated. Not yet human-reviewed. How we find the holding.

Opinion text

This opinion is nonprecedential except as provided by
Minn. R. Civ. App. P. 136.01, subd. 1(c).

STATE OF MINNESOTA
IN COURT OF APPEALS
A26-0043

Resolution Denying Petition for Environmental Assessment
Worksheet for Fischer Pit Expansion Project.

Filed August 3, 2026
Reversed and remanded
Schmidt, Judge

Vermillion Township
Resolution No. 25-12

Kyle S. Willems, James C. Kovacs, Bassford Remele, P.A. Minneapolis, Minnesota (for
relators Lisa Girgen and Rick Girgen)

Stephanie A. Angolkar, Andrew A. Wolf, Iverson Reuvers, Bloomington, Minnesota (for
respondent Vermillion Township)

Matthew S. Duffy, Mary Cate S. Cicero, Monroe Moxness Berg P .A., Minneapolis,
Minnesota (for respondent Pine Bend Paving Inc.)

Considered and decided by Beane, Presiding Judge; Smith, Tracy M., Judge; and
Schmidt, Judge.
NONPRECEDENTIAL OPINION
SCHMIDT, Judge
Relators Lisa and Rick Girgen challenge respondent Vermillion Township’s
decision that an environmental assessment worksheet (EAW) is not needed in connection
with a proposed mine. Relators argue that the township: (1) erred by determining that the
proposal did not trigger a mandatory EAW, and (2) acted arbitrarily and capriciously by
denying a citizens’ petition for an EAW. We reverse and remand.
2
FACTS
Respondent Pine Bend Paving Inc. operates a mine in Vermillion Township. The
mining site has been in operation since the 1980s and mines approximately 29 acres.
Pine Bend applied to the township for an interim-use permit to operate a new mining
and processing facility (the proposed mine) adjacent to the existing mine. The application
also requested that the site be rezoned from residential and agricultural to a designation
that would allow for mining. The proposed mine would consist of a 42-acre property,
33 acres of which would be used for mineral extraction.
Throughout the application process, the township worked with a consulting firm
named WSB. WSB’s community planner submitted a memorandum about the application
to the township stating that a mandatory EAW 1 is not required, but noted that the
“expansion of an existing mine may merit consideration of a discretionary [EAW].”
The township held a public hearing during which they discussed an EAW not being
mandatory and issues related to blasting and drainage. After the hearing, Pine Bend filed
an engineering supplement to the application, which addressed blasting, drainageway
options, and groundwater protection. The WSB engineer noted that any of the proposed
drainageways would require “modeling to confirm if there are any floodplain impacts.”
The Dakota County wetland coordinator issued a wetland-determination letter that
identified one potential wetland within the site of the proposed mine. That same day, a

1 An EAW is “a brief document which is designed to set out the basic facts necessary to
determine whether an environmental impact statement is required for a proposed action.”
Minn. Stat. § 116D.04, subd. 1a(c) (2024).
3
water-resources engineer from the Vermillion River Watershed Joint Powers Organization
recommended to WSB that the application be updated to meet the statutory requirements
of the Wetland Conservation Act because of the potential wetlands on the proposed site.
The township held a special public meeting to discuss the engineering supplement
and the wetland-determination letter. At the meeting, residents raised concerns regarding
blasting, seismograph monitoring, structural damage to houses, property values,
groundwater protections, a reclamation plan, and a stormwater prevention plan.
The Girgens, who live adjacent to the proposed mine, and other citizens petitioned2
the Environmental Quality Board to request that an EAW be prepared for the proposed
mine. The board sent the petition to the township after determining that the township was
the responsible governmental unit to decide whether an EAW was necessary.
WSB issued a responsive memorandum to the citizens’ petition, which
recommended that no EAW be completed. The memorandum concluded that the proposed
mine “will be subject to review and ongoing oversight through Vermillion Township as
well as other local and State regulatory authorities[,]” and that “existing review, approval,
and ongoing oversight processes are expected to identify, control, and if necessary, mitigate
for potential environmental impacts, including those outlined in the citizen petition.”

2 The full petition and its attachments are not part of the appellate record as the town did
not include it in the administrative record. The record only contains the signature pages of
the citizens’ petition, which referred to the proposed mine as the “Fischer Gravel Pit
Expansion Project” and “the proposed expansion of the aggregate mining operation in
Vermillion Township.” The Girgens did not move to correct or supplement the record
under Minn. R. App. P. 110.05.
4
Pine Bend also issued a responsive memorandum to the citizens’ petition, which
argued against an EAW because the proposed mine did not meet the requirements for a
mandatory EAW under the administrative rules. See Minn. R. 4410.4300, subp. 12(B)
(2025) (mandating preparation of EAW when a project “will excavate 40 or more acres of
land to a mean depth of ten feet or more during its existence” ). The memorandum also
stated that the citizens’ petition failed to provide material evidence that the proposed mine
had the “potential for significant environmental effects because of the ongoing public
regulatory authority and the mitigative measures that have been proposed” by Pine Bend.
The township held its final hearing on the application and thereafter issued
Resolution No. 25-12 rejecting the citizens’ petition. The resolution concluded that an
EAW was not mandatory under the administrative rules. It further determined that a
discretionary EAW was unnecessary because the proposed mine “will be subject to review
and ongoing oversight through Vermillion Township as well as other local, State, and
Federal regulatory authorities[,] . . . [which] are expected to identify, control, and if
necessary, mitigate for potential environmental impacts including those outlined in the
citizen petition.” The township also found that the evidence presented by the citizens’
petition failed to demonstrate that the proposed mine “will have the potential for significant
environmental effects.” The township also passed resolutions rezoning the site of the
proposed mine and approving the interim-use permit.
This certiorari appeal follows.
5
DECISION
The Girgens challenge the township’s decision to allow the proposed mine to
proceed without first completing an EAW. Before addressing the specifics of the Girgens’
challenge, we offer a brief overview of the applicable law.
Under the Minnesota Environmental Policy Act, the Environmental Quality Board
adopts rules governing the necessity for environmental review. See Minn. Stat. § 116D.04,
subd. 2a(b) (2024); Minn. R. 4410.0200–.6500 (2025 ). The appropriate responsible
governmental unit determines the level of environmental review required for a given
project. See Minn. R. 4410.0200, subps. 75–76 (defining responsible governmental unit).
An EAW or an environmental impact statement is mandatory if a project meets
certain thresholds. Minn. R. 4410.4300 (requiring EAW), .4400 (requiring environmental
impact statement), .4600 (exempting projects). An EAW is also required if the evidence
accompanying a petition signed by more than 100 citizens demonstrates “there may be
potential for significant environmental effects.” Minn. Stat. § 116D.04, subd. 2a(e) (2024).
Our review of a certiorari appeal is limited. We must affirm if the township engaged
in “reasoned decision[-]making” even if we may have reached a different result. Cable
Commc’ns Bd. v. Nor-West Cable Commc’ns P’ship, 356 N.W.2d 658, 669 (Minn. 1984).
We will reverse if (1) the decision reflects an error of law, (2) the findings are arbitrary and
capricious, or (3) the findings are unsupported by substantial evidence. Citizens Advoc .
Resp. Dev. v. Kandiyohi County Bd. of Comm’rs, 713 N.W.2d 817, 832 (Minn. 2006)).
Whether a decision reflects an error of law is a question that we review de novo.
See Minnesotans for Resp. Recreation v. Dep’t of Nat. Res., 651 N.W.2d 533, 538 (Minn.
6
App. 2002) (“The interpretation of statutes and rules and the application of statutes and
rules to undisputed facts are both questions of law that we review de novo.”). Whether a
decision is arbitrary and capricious requires us to assess whether the decision:
[a] relied on factors the legislature never intended it to
consider, [b] if it entirely failed to consider an important aspect
of the problem, [c] if it offered an explanation for the decision
that runs counter to the evidence, or [d] if the decision is so
implausible that it could not be ascribed to a difference in view
or the result of agency expertise.

Pope Cnty. Mothers v. Minn. Pollution Control Agency, 594 N.W.2d 233, 236 (Minn.
App. 1999). Whether a decision is supported by substantial evidence consists of reviewing
the record for: “1) such relevant evidence as a reasonable mind might accept as adequate
to support a conclusion; 2) more than a scintilla of evidence; 3) more than ‘some evidence’;
4) more than ‘any evidence’; and 5) evidence considered in its entirety.” Citizens Advoc.
Resp. Dev., 713 N.W.2d at 832 (quotation omitted).
The Girgens’ certiorari appeal raises numerous issues. We first address the Girgens’
arguments that the township improperly determined that the proposed mine constituted an
expansion of an existing mine, rather than treating the two mines as a “connected action.”
Within that analysis, we address the Girgens’ argument that even if the township properly
analyzed the proposed mine as an expansion, the decision was, nonetheless, arbitrary and
capricious as being unsupported by substantial evidence. Second, we combine the multiple
remaining issues that the Girgens raise into one issue. In doing so, we decline to address
many of the issues because we determine that the township applied the incorrect legal
standard when denying the petition for an EAW.
7
I. The township did not err in determining that the proposed mine would be an
expansion of the existing mine.

The Girgens argue that the township’s decision should be reversed because (A) the
proposed mine constituted a “connected action” and (B) the proposed mine was not an
expansion. We address each argument in turn.
A. The “connected action” argument is forfeited and fails.
The Girgens argue that the township erred by analyzing the proposed mine as an
expansion of an existing mine, rather than treating the two mines as a “connected action.”
If viewed as a connected action, the Girgens contend that the combined mined acreage
exceeds the threshold for a mandatory EAW. See Minn. R. 4410.4300, subp. 12(B).
The Girgens, however, raised the connected-action argument for the first time on
appeal. A party may neither raise a new issue on appeal, nor “obtain review by raising the
same general issue litigated below but under a different theory.” Thiele v. Stich,
425 N.W.2d 580, 582 (Minn. 1988); In re A.D., 883 N.W.2d 251 , 261 (Minn. 201 6)
(quoting Thiele in certiorari appeal). The connected-action argument is forfeited.
The connection-action argument also fails because the Girgens did not meet their
statutory burden to present material evidence to support their petition for an EAW on these
grounds. See Minn. Stat. § 116D.04, subd. 2a(e). Because they failed to assert a
connected-action theory before the township, it follows that the Girgens did not meet their
burden to present material evidence in support of a theory they never raised. See
Kristufek v. City of Breezy Point, No. A06-1220, 2007 WL 1674557, at *6 (Minn. App.
June 12, 2007) (affirming because there was no evidence presented to show that an EAW
8
was mandatory).3 Thus, the connected-action argument fails because the Girgens did not
carry their burden to prove that the proposed mine constituted a “connected action” such
that the proposed mine required an EAW.
B. The township’s “expansion” decision was not based on legal error,
arbitrary and capricious, or unsupported by substantial evidence.

The Girgens argue that the township’s decision to classify the proposed mine as an
“expansion” was (1) an error of law and (2) unsupported by the evidence. We disagree.
First, the township did not commit any errors of law when it decided that the
proposed mine constituted an “expansion.” The administrative rules define project
“expansion[s]” as “an extension of the capability of a facility to produce or operate beyond
its existing capacity.” Minn. R. 4410.0200, subp. 28. Here, the township found that Pine
Bend operated an existing mine on the adjacent property to the south of the proposed mine.
The township found that the proposed mine “will allow for expansion of an existing mine
with an existing haul route and infrastructure that is already present in the vicinity.” The
township’s classification of the proposed mine as an “expansion” was not erroneous.
The township also did not err as a matter of law when analyzing whether the
proposed mine triggered the threshold for a mandatory EAW. The t ownship determined
that an EAW was not required because the existing mine had been in operation for more
than three years before the application was submitted. Given this determination, the rule
did not require the original mine to be included in the size calculation for whether an EAW
was mandated. See Minn. R. 4410.4300, subp. 1(B). Because the proposed mine would

3 We cite Kristufek for its persuasive value. See Minn. R. Civ. App. P. 136.01, subd. 1(c).
9
excavate 33 acres , the township correctly determined that an EAW was not required
because the proposed mine was below the 40-acre threshold that mandates an EAW. See
id., subp. 12(B). Thus, the township did not err in determining that the “expansion” did
not meet the threshold for a mandatory EAW.
Second, the township’s decision is supported by substantial evidence. The proposed
mine had consistently been treated as an expansion. The initial application presented the
proposal as an expansion of an existing mine. The township’s consultants assessed the
proposed mine as an expansion. Even the signature pages on the citizens’ petition called
the proposed mine an expansion. The record also reflects that the site of the proposed mine
is adjacent to the existing mine and will share operations such as crushing, stockpiling,
recycling, loading, and hauling. The record contains more than a scintilla of evidence.
Therefore, the township’s decision is supported by substantial evidence.
II. The township erred by applying the wrong standard for determining whether
the petition demonstrated a basis to require an EAW.

The Girgens argue that the township’s decision to deny their petition for an EAW
was arbitrary and capricious because material evidence shows that the proposed mine may
have the potential for significant environmental effects. The Girgens assert that the most
significant issues that were arbitrarily dismissed by the township included: the lack of
modelling to manage the drainageway; the identification of a potential wetland on the site
and relevant studies being pushed off to the future; and concerns about blasting and its
effects on human health. Because we conclude that the township erred by applying the
wrong standard in assessing these concerns, we remand to the township.
10
The statute provides that an EAW must be prepared for a project when material
evidence demonstrates that “there may be potential for significant environmental effects.”
Minn. Stat. § 116D.04, subd. 2a(e) (emphasis added). The township, however, determined
that “the evidence presented fails to demonstrate the [proposed mine] will have the
potential for significant environmental effects.” (Emphasis added.) The legal error in the
township’s analysis turns upon the distinction between “may be” and “will have.”
The legislature did not define “may” as used in this statute. We turn to the
dictionary. See McBee v. Team Industries, Inc., 26 N.W.3d 847, 853 (Minn. 2025) (using
dictionary to determine a word’s common usage). The American Heritage Dictionary
defines “may” as “used to express possibility or probability: It may rain this afternoon.”
The American Heritage Dictionary of the English Language 1086 (5th ed. 2018). The
dictionary defines “will” as (1) “used to indicate simple futurity: They will appear later”
and (2) “used to indicate likelihood or certainty: You will regret this.” Id. at 1982.
Applying these dictionary definitions, we conclude that the township’s use of “will
have” improperly imposed a certainty standard on the Girgens’ petition. The correct
scrutiny that must be given to the Girgens’ petition is a less-certain standard: whether the
petition demonstrated that the proposed mine has the possibility of the “potential for
significant environmental effects.” Minn. Stat. § 116D.04, subd. 2a(e) (“there may be
potential for significant environmental effects” (emphasis added)).
The more-certain standard that the township applied would come later in the process
should the t ownship, on remand, determine that an EAW is necessary. Whether the
proposed mine will have the “potential for significant environmental effects” is a question
11
that must be answered when assessing whether an environmental impact statement is
needed, which occurs after an EAW is completed. See Minn. Stat. § 116D.04, subd. 2a(a)
(2024) (requiring an environmental impact statement when “there is potential for
significant environmental effects”); see also Citizens Advoc. Resp. Dev., 713 N.W.2d at
825 (“[i]f, after reviewing the EAW, the [responsible governmental unit] decides that the
project does have the potential for significant environmental effects, the [responsible
governmental unit] is required to issue a positive declaration indicating that an
[environmental-impact statement] must be completed” (quotation omitted)).
Here, the township applied the higher standard too early in the process. On remand,
the township must first assess the Girgens’ petition under the correct standard. Minn. Stat.
§ 116D.04, subd. 2a(e). If the township determines that an EAW is necessary, it will then
use the completed EAW to determine whether the proposed mine will have the potential
for significant environmental effects. Id., subd. 2a(a). Thus, we conclude that the township
erred in applying the wrong standard when it assessed the potential for significant
environmental effects at this earlier stage.
Given the application of the incorrect standard, we cannot meaningfully review the
Girgens’ appellate arguments that the township’s decision was arbitrary and capricious or
unsupported by substantial material evidence. As such, we reverse and remand the matter
to the township to apply the correct legal standard to the citizens’ petition and to issue a
revised decision. See In re PolyMet Mining, Inc., 965 N.W.2d 1, 12 n.14 (Minn.
App. 2021) (noting that remand is consistent with separation-of-powers concerns
underlying limited review on certiorari), rev . denied (Minn. Sept. 30, 2021); Minn. Stat.
12
§ 14.69, subd. (d) (2024) (authorizing remand in certiorari review when petitioners’
substantial rights were affected by “other error[s] of law”); In re A.D., 883 N.W.2d at 258
(“Remand is appropriate to permit further evidence to be taken or additional findings to be
made in accordance with the applicable law.” (quotation omitted)). The township has the
discretion to decide whether to reopen the record to permit additional evidence.
Reversed and remanded.